Sandridge Avenue reconstruction starts | ParkRecord.com
YOUR AD HERE »

Sandridge Avenue reconstruction starts

Cody Ekker Construction won a City Hall contract for the redo of Sandridge Avenue, a tucked-away Old Town street, and has started the work.

The workers will tear out the existing roadway on Sandridge Avenue and replace it with a new one. The crew will also replace water and natural-gas lines as well as plant landscaping at the nearby Marsac Avenue-Hillside Avenue intersection.

Matt Cassel, the Park City engineer, expects the work to cost between $350,000 and $360,000, approximately half of what had been budgeted.

Cassel says the work is scheduled for completion by mid-September.


Support Local Journalism

Support Local Journalism

Readers around Park City and Summit County make the Park Record's work possible. Your financial contribution supports our efforts to deliver quality, locally relevant journalism.

Now more than ever, your support is critical to help us keep our community informed about the evolving coronavirus pandemic and the impact it is having locally. Every contribution, however large or small, will make a difference.

Each donation will be used exclusively for the development and creation of increased news coverage.

 

Start a dialogue, stay on topic and be civil.
If you don't follow the rules, your comment may be deleted.

User Legend: iconModerator iconTrusted User